Question on scope verification
Can anyone please let me know
Why is the answer a & not c?
James is a senior manager at a telecommunications company. He is currently managing a project developing a voice over IP gateway that addresses the challenges facing service providers deploying packet based voice networks. All of the technical work has already been completed on the project and the project is in the closing phase. Which of the following should be performed at this stage?
a)Document lessons learned
b)Ensure that the project is integrated with other projects
c)Perform scope verification
d)Verify the quality of process
Explanations:
Answer (a) Document lessons learned is also an activity that is performed during the closing process


admin
Thu, 07/17/2014 - 03:16
Permalink
The key here is that project
The key here is that project is in the closing phase. Secondly Verify scope has not been changed to Validate scope in PMBoK5 and its not a closing phase activity.
naeem.farooqui
Thu, 07/17/2014 - 07:43
Permalink
Correct Answer -A
Scope varification is performed during Monitoring Controlling Process group.
Option A (Document Lessons Learned) is the only option performed during Closing process group from given choices.