Question

you are managing a construction project and your budget is $20000, you have spent 17000 and 75% of project is complete , a new project budget of 25000 is approved . What should be your cost performance if you want to complete your project with the new budget . a 1.667 b 0.882 c 0.625 d 0.521

acurtpmp's picture

TCPI, using EAC denominator vs. BAC since there is a new budget. TCPI= (20000-15,000)/(25,000)-(17000) = .625