When is it best time to have project kick off meeting?

a. At the begining of the project

b. at the start of each phase of project

c. when each deliverable is created

d. When communication management plan is approved

C and D are eliminated. Among a and b I feell "a" is best. Which option is best ?

gomsy's picture

At the start of each phase of project, we need to have a kick off meeting to have/set better understand of all stakeholders expectations.

any views as why not D?