Need help on a question on TCPI
Submitted by nidhitripathi on Wed, 08/03/2011 - 01:51
Hi All,
Encountered this question on Free PM Exam Simulator and am not able to get to the answer they have posted.
Here is the question:
You are managing a construction project and your project budget is $20,000. You have spent $17,000 so far and the project is 75% complete. A new project budget of $25,000 has been approved. What should be your cost performance if you want to complete the project within the new approved budget?
Options: (1) 1.667 (2) 0.882 (3) 0.625 (4) 0.521
Ans: (3) - 0.625.
Would appreciate if anyone could help with this.
Thanks
Nidhi
Forums:


admin
Wed, 08/03/2011 - 04:24
Permalink
Check this page , you should
Check this page , you should be able to figure out the answer
http://www.pmzilla.com/tcpi
sili18
Wed, 08/03/2011 - 17:35
Permalink
Answer should be 0.882
I believe the answer should be 0.882
Follow my analysis... let me know if that has any wrong..
Cost Performance = EV/AC
Here you have AC as $17000
Need to calculate the EV. EV should be the %Completion multiplied by BAC. So it should be 75% of $20000 which is $15000.
So CPI = $15000/$17000 = 0.882
nidhitripathi
Wed, 08/03/2011 - 19:23
Permalink
I did the same thing but the
I did the same thing but the answer posted by the site is not 0.882.
aaron
Thu, 08/04/2011 - 16:52
Permalink
Here you are being asked to
Here you are being asked to calculate the TCPI using the formula BAC-EV/EAC-AC
Please note EAC in denominator because of revised budget.
so TCPI is 20K - 15K/25K-17K = 5000/8000 = .625
nidhitripathi
Thu, 08/04/2011 - 17:18
Permalink
Thanks a lot! This really
Thanks a lot! This really helps!