Calulation Based Question
Submitted by munishmsh on Sat, 08/06/2011 - 07:01
Hi
Would you please let me know how to do the calculation for the below question.
A Cost-plus incentive fee contract has the following contract elements Target cost = $10,000,000 Target Profit = $800,000 Optimistic Cost = $8,000,000 Optimistic Profit = $1,000,000 Pessimistic Cost = 12,000,000 Pessimistic Profit= $1,600,000 If the seller completes the project at an actual cost of $10, 200,000, what is the overall price for the buyer if the over-run share ratio is 60/40?
Regards
Msh
Forums:


munishmsh
Sat, 08/06/2011 - 07:17
Permalink
Here goes one more You are
Here goes one more
You are performing variance analysis on the material used in the project. What is the usage variance for the following? Budgeted price per unit =$200 Actual Price per unit=$250 Budgeted Quantity=250 Actual Quantity=225
Deepti
Sat, 08/06/2011 - 17:03
Permalink
Answer
Hey Manish
What's the answer for both the q..
I think it's c for both i.e. 1092, and -6250..
munishmsh
Sat, 08/06/2011 - 22:50
Permalink
Hey Deepti its c and a. would
Hey Deepti
its c and a. would you please explain atleast first answer.
Deepti
Sun, 08/07/2011 - 03:26
Permalink
for 1st
Actual cost + Target Profit - (Actual cost- Target Cost) * 40%
I believe this optimistic and pessimistic stuff is extra data...