WBS Activity
Submitted by alexmcduffie on Thu, 04/11/2013 - 21:25
You've constructed the WBS for your recent project. You've requested that the subproject managers report to you in three weeks with each of tehir individual WBS contructed. Which statement is not true regarding the subproject managers' WBS?
A) The work package level is decomposed to create the activity list.
B) The work package level is the lowest level in the WBS
C) The work package level faciliaties resource assigments.
D) The work package level facilities cost and time estimates.
Forums:


Geethika
Thu, 04/11/2013 - 22:02
Permalink
C..
A) The work package level is decomposed to create the activity list. - true
B) The work package level is the lowest level in the WBS - true
C) The work package level facilitates resource assigments. - not true (WBS is not used for this purpose)
D) The work package level facilitates cost and time estimates. - true
sspawar
Thu, 04/11/2013 - 23:33
Permalink
wpkges may provide
wpkges may provide information of resources required.
But Assignment means -- very specific like Mr X will do this job from this date to that date.
Definitely this is not a part of wbs/wpackages/control point/control account