output of activity duration
Submitted by Jp2786 on Wed, 04/23/2014 - 20:56
Which of the following is an output of activity duration?
A A WBS
B An activity list
C A network diagram
D A project schedule
What do you guys think?
Cheers
Jp
Forums:


philstinnet
Wed, 04/23/2014 - 21:19
Permalink
The answer is D.If i know
The answer is D.
If i know that an activity takes 5 days (aka - activity duration), i can use that to get my schedule.
Other choices can not come out from activity duration.
Thanks.
Jp2786
Wed, 04/23/2014 - 21:28
Permalink
Question must be wrong
Hey I think this question mus tbe wrong. Becasue as a a part of develop schedule we will get project schedule. Network dia is a part of sequencing activities.
I think the question should read activity definition then the asnwer would be B.
Cheers
Jp
philstinnet
Wed, 04/23/2014 - 21:44
Permalink
My humble 2 cents -I feel
My humble 2 cents -
I feel that the question is just right.
And, i really liked this questions.
It is not like the other questions where we see that the language is confusing or the story before the question is just given to confuse the examinee.
A project can very well have just one activity. There is no book which says that a project needs to have at least this many number of activities to call it a project.
If i know the duration of an activity, i can use it to develop my schedule. I can not use it to develop the network diagram, activitiy list or WBS.
What is the correct answer ?
Thanks
Jp2786
Wed, 04/23/2014 - 22:15
Permalink
Well said.
I agree with you. Answer should be D.
I'm sorry dude, I dont have the answer with me, but I humbly accept your reasoning.
Cheers
Jp
sunku65
Sat, 04/26/2014 - 07:41
Permalink
Answer is D:We can think the
Answer is D:
We can think the only one activity in the project. (i.e. Hammock). then answer is D.