Project manager on a complex industrial automation project has been recently changed. The project is being delivered from different engineering centers across the world. The last performance report indicates that the project is running over budget but schedule performance is better than planned. What should the newly appointed project manager do first?
A)Understand the diverse cultural dynamics of the project
B)Review scope management plan
C)B)Review cost management plan
D)B)Review schedule management plan
Forums:


BK
Sun, 05/19/2013 - 07:14
Permalink
A?
A?
vijayavadrevu
Sun, 05/19/2013 - 07:15
Permalink
Actually I too have answered
Actually I too have answered as A. But the answer by the author is B i.e., review scope management plan. Hence posted the question
rwmv
Sun, 05/19/2013 - 07:35
Permalink
B
Answer-B because the question is really talking performance report---its running over budget and schedule performance is better. Scope has to be reviewed to se why its over budget. Scope will only tell you if there are added resources at additional cost.
cnppmp
Sun, 05/19/2013 - 12:21
Permalink
B
B...looking at the scope management plan...since it has all relevant information like scope baseline ect.
regards
CN Patil
sanskrit
Mon, 05/20/2013 - 13:18
Permalink
Technically scope management plan does not contain scopebaseline
Technically scope management plan DOES NOT contain scope baseline,
Scope Management Plans tells you how the scope will be managed
cnppmp
Sun, 05/19/2013 - 12:25
Permalink
This is tricky
continuing to my previous response...where I have chosen B option.
We look for very obvious reason from first part of the quetsion. Second part of the question actual speaks about the main issue..anything related to performance needs to be looked at while we are in executing phase. This phase is where we get lot of performance reports. This is why I picked B above...
Regards
CN Patil
pmpnewster
Sun, 05/19/2013 - 12:41
Permalink
Why not option C) Review
Why not option C) Review cost management plan ?
Regards.
sanskrit
Mon, 05/20/2013 - 13:23
Permalink
Surprised with the Answer
Technically scope management plan DOES NOT contain scope baseline.
Scope Management Plans tells you how the scope will be managed, Scope Baseline is totally different thing it consists of (WBS , WBS Dictionary and Project Scope Statement)
But Adding to that, From all the options available this might be the only somewhat close answer shuld be Cost management Plan , to see how the cost estimates will be done and all