PM study free test - 3 quick questions

Hi,


I'd appreciate an explanation as to why the correct choice is 2 for


Control Quality is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. To evaluate control quality output data, the project team must ideally have a working knowledge of:


  


  Choice 1  Prevention and inspection 


 


  Choice 2  Sampling and probability 


 


  Choice 3  Special causes and random causes 


 


  Choice 4  Tolerances and control limits 


 Also, can you please help with why the correct choice is 3 for:


Due to a shift in company objectives, your project is expected to terminate before completion. Team members are scared and disappointed as they learn they will be out of a project. As the project manager, what should you do in this situation?


 


 


  Choice 1  Ignore them, they are no longer your concern.


 


  Choice 2  Talk to the sponsor to try to reinstate the project.


 


  Choice 3  Delegate to HR for post project staff assignment.


 


  Choice 4  Call them for a meeting to discuss team members concerns.


Finally, is it worth paying for the other PM Study exams?


Thanks!

 for first question correct answer is Choice 2, because Control Quality deals with sampling. 

Choice 2  Sampling and probability

for second questions, answer is Choice 4. 

Choice 4  Call them for a meeting to discuss team members concerns.

i took all paid exams from PM study, not so great or not so bad.