PM study free test - 3 quick questions
Hi,
I'd appreciate an explanation as to why the correct choice is 2 for
Control Quality is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. To evaluate control quality output data, the project team must ideally have a working knowledge of:
Choice 1 Prevention and inspection
Choice 2 Sampling and probability
Choice 3 Special causes and random causes
Choice 4 Tolerances and control limits
Also, can you please help with why the correct choice is 3 for:
Due to a shift in company objectives, your project is expected to terminate before completion. Team members are scared and disappointed as they learn they will be out of a project. As the project manager, what should you do in this situation?
Choice 1 Ignore them, they are no longer your concern.
Choice 2 Talk to the sponsor to try to reinstate the project.
Choice 3 Delegate to HR for post project staff assignment.
Choice 4 Call them for a meeting to discuss team members concerns.
Finally, is it worth paying for the other PM Study exams?
Thanks!


SREENU76
Tue, 11/05/2013 - 11:17
Permalink
for first question correct
for first question correct answer is Choice 2, because Control Quality deals with sampling.
Choice 2 Sampling and probability
for second questions, answer is Choice 4.
Choice 4 Call them for a meeting to discuss team members concerns.
i took all paid exams from PM study, not so great or not so bad.