A project manager is working on a complex project with people from around the world. The project schedule is set, but the tasks require detailed integration with other tasks being done by the buyer. What is the BEST thing the project manager could use to control this situation?


1.work authorization system


2. configuration management system


3.historical information


4. change control board


 


answers will be helpful!

Work authorization system allows the PM to dictate when each task is authorized to start.  PM can decide this based the Integration Management process


Chandra

I agree that the answer is 1 - Work Authorization System. Read the definition of Work Authorization System in the PMBOK glossary.