PMP QUestion on Project Selection and Earned Value
Submitted by manjubn7628 on Thu, 09/02/2010 - 11:56
Can Some one Please answer these Questions..
Q1. Here are a list of Projects ?
Project Investment Costs Chance of Winning
Proj A 100 $ 30 %
Proj B 200 $ 40 %
Proj C 300 $ 50 %
Which one do you select ?
Q2. What does it mean when both Cost Variance CV and Schedule Variance SV are 0.. It can be On-Budget ..but that was not listed as an option ?
Forums:


dinesh_babu_r
Thu, 09/02/2010 - 12:53
Permalink
Hi Reg Q1: I think Proj C
Hi
Reg Q1: I think Proj C might be the answer, as the Chance of winning is 50%. Usually for project selection we have
n no's of techniques, like cost-benefit analysis, NPV(Higher Net Present Value) etc. the question appears to be
a variant of the cost-benefit with 50% benefits. Others please correct me if wrong.
Reg Q2, we need to see the options.
, as atleast an option would have indicated the same meaning (On Budget - On Schedule) message in a different way/tone.