PMP Question - Which one is correct?
Submitted by Thinhphung on Sun, 05/25/2014 - 00:57
My Friend,
I've got this question with ambiguous answer. Could you please help!?
Which of the following is the correct order of actions that you take during the Closing processes?
A. Get formal acceptance, release the team, write lessons learned, close the contract
B. Write lessons learned, release the team, get formal acceptance, close the contract
C. Get formal acceptance, write lessons learned, release the team, close the contract
D. Get formal acceptance, close the contract, write lessons learned, release the team
Source: www.quizlib.net.
Thinh
Forums:


sanjay077
Sun, 05/25/2014 - 05:17
Permalink
hi
Ans : D
sunku65
Sun, 05/25/2014 - 07:47
Permalink
Observe the choices A,B & C,
Observe the choices A,B & C, The Close contract is the last one shown here. Hence, all of these three choices are anyway is wrong.
Finally, the leftover choice is D. (i think its PMBOK4 version).
Thanks,
Lax
Thinhphung
Tue, 05/27/2014 - 02:48
Permalink
Thanks for the explanation,
Thanks for the explanation, Lax! I think PMBOK 4 or 5 have the same answer, correct? I still not have PMBOK5 yet so not sure what you want to imply PMBOK4
Frances Tessler
Sat, 10/04/2014 - 22:07
Permalink
Close Project or Phase
D is correct answer.
Sandy10001
Wed, 10/08/2014 - 16:49
Permalink
Details, Details!
D is correct.
First you need to have acceptance of the product(s). If there is a contract within the project, this would need to be closed after formal acceptance by the customer. You want the team to participate in lessons learned so that should occur before releasing the team.