PRELIMINARY PROJECT SCOPE STATEMENT
Dear KK and others
Last time I came across this question. A tougher series, answer is D - Preliminary Project Scope Statement.
I answered - B, - PROJECT CHARTER found wrong.
I further studied regarding PPSS.
And a very fine and important information came out is that - PMBOK 4 - does not recognize the term PPSS. It was in E3 and now deleted in E4.
So be aware if you found any such option or reference - verify it with PMBOK . Refer "P352PMBOK®E4"
---------------------------------------------------
Q] Your company’s project review committee (PRC) asked you to present your project’s objectives, requirements, and deliverables at its next meeting. You need to prepare which one of the following documents?
A. | WBS | |
| ||
B. | Project charter | |
| ||
C. | Product description | |
| ||
D. | Preliminary project scope statement | |
| ||
Explanation:
The preliminary project scope statement provides stakeholders with a common understanding of the scope of the project and is a source of reference for making future project decisions.