Probability and Impact matrix is a part of OPA or EEF?
admin
Wed, 10/19/2016 - 07:12
Permalink
I didn't get your question
If the probability and impact matrix is at org level and available for reference usage it will be part of OPA, and projects will have to refer it for risk qualitative assesment.