Procurment Calc. Question from Lehman 75Q

From Lehman 75Q.. can someone pls explain how to calculate PTA (Point of Total Assumption)

 

 

16. You are running a project for a customer based on a cost-reimbursable contract with the following terms:
 
Target costs:     $ 1,000,000
Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= point of total assumption, break point) of the project?

 

 1125000

 Thx ... What equation are you using to calc?

 PTA = ((Ceiling Price - Target Price) / Buyer Share %) + Target Cost

= ((1,200,000 - 1,100,000) / 0.8) + 1,000,000

= 100,000 / 0.8 + 1,000,000

= 125,000 + 1,000,000

= 1,125,000

 Thanks! Very helpful..

by the way, Rajesh Nair's notes say :

 

Point of total assumption (PTA): is the point at which the seller assumes the costs. Only applicable to FPIF contracts.
The PTA is when the seller becomes responsible for all costs. The formula uses the ceiling and target prices and the buyer's cost sharing portion. The ceiling price is the most pessimistic cost based on reasonable factors. Anything above the ceiling price is considered to be due to lack of oversight by the seller.

 

In Lehman's question... It states this is a cost reimbursable contract. Can PTA be used for both FIXED and Cost Reimbursable? 

 PTA = ((Ceiling Price - Target Price) / Buyer Share %) + Target Cost

PTA is in FPIF contracts..

Articles in deepfriedbrain may give more insight on PTA

 http://www.deepfriedbrainproject.com/2009/09/point-of-total-assumption-pta-fpif-pmp.html

crushPMP's picture

Cant find anything like a PTA in the PMBOK v4. Can PMI exams ask questions and concepts not in PMBOK?

Yes questions related to PTA can be asked in exam

The point of total assumption (PTA) is the point above which the seller bears all the losses of an additional cost overrun on a fixed price 'incentive fee' (FPIF or FPI) contract. 
 
Knowledge Area: Procurement Management
Process Group: Planning
 
Thanks