 do we need to create project charter for every phase of the project?

saketbansal's picture

No, Project Charter is for Project, and this is the only document which is not expected to change through out the project. No Input called Approved Change Request in this process :-) .

 

PMBOK 5 Page 71 

"The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. "

 i also agree with this ..i got this question in one mock test and the answer was "yes" ..i wass bit surprized with the answer..however... in my understanding " the project phase descision will be done in planning process group and does not need a new charter for the net phase.

saketbansal's picture

Be carefull with mock test... we have so many free...but many junk and just to confuse you and not to make any help in your certification journey