Project, Program and Portfolio
Dear All,
As I am preparing for PMP, I am reading PMBOK and trying to simulate it with my current work and culture.
I am trying to understand from my personal experience but I want to validate it.
Based on my current enagagements. following is my understanding about project, program and portfolio
Please correct wherever possible
Portfolio – Organization XYZ having strategic company objective to gain 1 Billion $ revenue
Portfolios consisting of following items
1)
Project 1– recruit more and more sales people
2)
Subportfolio 2 - ERP projects
3)
Subportfolio 3 - CRM projects
a.
Program (3.1) - CRM project in Real Estate domain
i.
Project – Real estate project for client 1
ii.
Project – Real Estate project for client 2
(inter- dependency management in program management so that modules developed for client 1 can be sold to client 2)
b.
Program (3.2) – CRM projects for Insurance companies
Interdependency between subportfolio 2 and sub portfolio 3 – integration of these two systems for few clients
No interdependency between Project 1 and others
There is a line in PMBOK – What does that mean if I relate to above example
“Projects within a program are related through the common outcome or collective capability.
If the relationship between projects is only that of a shared client, seller, technology, or resource, the effort should be managed as a portfolio of projects rather than as a program.”