Jack is the project manager of a project that is halfway through the execution. Jack is currently looking at the schedule of work. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. This relates to which of the following processes?

  1. Control Quality

  2. Develop Schedule

  3. Control Scope

  4. Control Schedule

 

Can somebody explain the logic behind this.

Hey, Im still learning so I might be wrong,

Is the answer "Develop schedule", I selected this choice becuase if Jack is adjusting schedule milestone without going through Intergrated change control then he is still in the planning stage (baseline is not appoved yet.) if the baseline is approved then he will have to go CCB board to get it changed. 

The answer is D. I didnt get the logic behind this.

The question clearly mension that "....halfway excecuting the project..".

More over the milestomes has zero duration no need change request.

Answer is D.

admin's picture

The planning stage is over and the PM is half way in execution stage so it should be Control Schedule. 

Yes My bad... I didnt read the question properly. Thanks all.