Question 1 Which of the following are the primary costs of meeting project quality requirements?
- Expenses incurred while performing the Project Quality Management Knowledge Area
- Expenses incurred while performing quality activities
- The costs to produce the product or service of the project
- Failure costs
Forums:


prashant.spce
Fri, 08/17/2012 - 04:42
Permalink
2. Expenses incurred while
2. Expenses incurred while performing quality activities
sspawar
Fri, 08/17/2012 - 06:12
Permalink
Answer would be
Answer would be 2
8.1.2 Plan Quality: Tools and Techniques
.1 Cost-Benefit Analysis
The primary benefits of meeting quality requirements can include less rework, higher productivity, lower costs, and increased stakeholder satisfaction.