Question

Question 1 Which of the following are the primary costs of meeting project quality requirements?



  1. Expenses incurred while performing the Project Quality Management Knowledge Area

  2. Expenses incurred while performing quality activities

  3. The costs to produce the product or service of the project

  4. Failure costs

 

prashant.spce's picture

2. Expenses incurred while performing quality activities

Answer would be 2




  1.  

  2. Expenses incurred while performing quality activities


8.1.2 Plan Quality: Tools and Techniques


.1 Cost-Benefit Analysis


 


The primary benefits of meeting quality requirements can include less rework, higher productivity, lower costs, and increased stakeholder satisfaction.


 


A business case for each quality activity compares the cost of the quality step to the expected benefit.