Question
Submitted by sspawar on Fri, 08/17/2012 - 11:50
The difference between being proactive and reactive is the development of a:
Payoff table
Range of probabilities
Range of payoffs
Contingency plan
Is this question asked correctly?
Forums:


gvenki02
Fri, 08/17/2012 - 17:49
Permalink
Contingency plan
Answer D:
In case of Risk acceptance strategy, proactive acceptance includes developing a 'Contingency plan', where as a passive acceptance is to deal with it when the Risk happens.
Thanks,
Venkat
sspawar
Sat, 08/18/2012 - 01:01
Permalink
my q i different , read last
My q is different , read last line.