Question about CPI and SPI (oliver lehmann)
Hello All
|
124. Post mortem earned value analysis of a project showed the following data: SPI: 0.78 CPI: 1.00 What is this telling you? 124 o The entire work of the project has been finished behind schedule and on budget. o The entire work of the project has been finished ahead of schedule and on budget. o The project has been terminated before completion. At that time it was behind schedule and on budget o The project has been terminated before completion. At that time it was ahead of schedule and on budget. |
(this is from oliver lehmann)The answer is c. I understand the "on budget" part, could someone explain, how can we infer that the project has been terminated before completion?


danang_monkey
Wed, 02/19/2014 - 06:07
Permalink
The Walking Dead "Project"
Post Mortem:
Def: a discussion or analysis of something after it has ended