Question about Earned Value on Exam
Submitted by pags51 on Thu, 12/01/2011 - 18:51
I'm using Rita right now, and when calculating EAC the questions do not specify if the test taker should calculate EAC at the budgeted rate, at the present CPI, SPI, or both. It just asks for EAC, and depending on how you do it, you're going to get differing answers. For the exam, is it clarified which approach to take, or does the test taker need to assume which way it should be calculated?
Thanks