Question on Equipments
Submitted by heuy59 on Wed, 06/04/2014 - 10:48
A customer returns all materials including epuipments after work completed as indicated in the contract or procument. Which process group will you find this and where will this information be be documented (Equipments)? .........
Forums:


Jp2786
Wed, 06/04/2014 - 18:36
Permalink
What are the options?
What are the options?
Without it, I would say close proc and records management system respectively.
Jp2786
Wed, 06/04/2014 - 22:16
Permalink
Typo in the previous comment
Typo in the previous comment.
I meant to say PM will use records mgmt system to update procurement docs.
I would guess close proc process and procurement docs.
admin
Thu, 06/05/2014 - 03:50
Permalink
Seems simple, what are the
Seems simple, what are the options, is it confusing ?
sunku65
Sat, 06/07/2014 - 09:16
Permalink
Machinery & Equipment lists
Machinery & Equipment lists in a separate list called Annexxure to a Contract. The list of this equipment contains in the procurement documents.
Frances Tessler
Sat, 08/02/2014 - 14:47
Permalink
Close Procurement
The only place where equipment would be returned on a contract is when the work was completed. In Close Procurement a Procurement Audit is done to determine/verify if all contract items and the Procurement Statement of Work was met. As part of the Procurement Audit sign off would occur and that is when you do lessons learned, create the Procurement File update OPA, final payouts, and return all equipment as well as release the recourses as you don't need them any longer.
PMP Fox
Mon, 08/04/2014 - 08:35
Permalink
process group Closing
process group Closing
Knowledge Area : Project Procurement Management
Analyzing
1- Customer can't take any materials including equipment's without a contract
2- Contacts are part of project documents
3- Contacts are controlled by Procurement management processes
4- Since the customer is returning the materials and equipment's that means he is intending to close the close the contract as it had been fulfilled.
:)
5- Closing Procurement will control the above action