Question - Project charter change
Submitted by eldrin.connery on Thu, 09/23/2010 - 04:49
Who can approve of changes to any of the primary constraints on your project such as scope, budget, or timeline?
a. The Change Control Board
b. The sponsor
c. Senior management
d. Key stakeholders
Forums:


admin
Fri, 09/24/2010 - 08:08
Permalink
Change control board - it can
Change control board - it can have sponsor, Sr. management as required on the board.
PMP King
Sat, 10/23/2010 - 11:51
Permalink
Question - Project charter change
Only project sponsor can change Project Charter. Sponsor could be in CCB, sr. management and can also be key stakeholder but as per PMBOK, only sponsor can change charter.
bpp9614
Tue, 10/26/2010 - 16:31
Permalink
Only Sponsor
Sponsor may/may not be part of CCB. Hence Sponsor must approve any change to Charter. Do you remember who signed charter? Any signed document cannot be changed by others :-)
raj9
Wed, 10/27/2010 - 15:46
Permalink
Change control board
Correct answer is change control board.
Project charter includes High level requirement. It does not have scope. Scope is defined in Project management plan.This question pertains to project management plan.(It has scope,budget & timeline).In PMP exam -No question has title like Projct charter change or schedule change. It is the understanding of individual.
Raj
bpp9614
Wed, 10/27/2010 - 21:22
Permalink
Correct. As per the
Correct. As per the question, the answer is CCB.
pmalik
Fri, 09/22/2017 - 07:23
Permalink
Change Management
You should refer to the following article to understand the Change Management Process. It will help you in answering your question.
9 Rules to Answer PMP Change Management Questions