Q. In planning your project, which would generally have the highest priority: quality, cost, or schedule?
A. Cost is most important, quality next, and then schedule.
B. Quality is more important than cost or schedule.
C. Schedule is most important, quality next, and then cost.
D. It should be decided for each project.
Forums:


admin
Sat, 08/18/2012 - 12:58
Permalink
D - This is critical success
D - This is critical success factor and its decided case by case for each project.
godara0302
Mon, 08/20/2012 - 05:18
Permalink
B is the perfect answer
B is the perfect answer
shiva_rk
Mon, 08/20/2012 - 05:27
Permalink
D - It varies from project and application area
D - It varies from project and application area