Which of the following statements concerning quality planning is correct?
A. Quality planning should be performed regularly throughout the project.
B. Quality planning is done to compile a risk management plan.
C. Quality planning is done only during project planning.
D. Quality planning is not considered during project execution.
Forums:


Jp2786
Wed, 06/04/2014 - 18:07
Permalink
I would go with A
I would go with A.
IMO, C and D are wrong becuase Q Planning can be done at any point in time during the project (let say a new govt regulation that needs to be considered for your project so you will plan quality).
w.r.t to B i think its not mandatory to complete Q.P to complete Risk management plan.
What the correct answer?
admin
Thu, 06/05/2014 - 03:48
Permalink
Yes A seems to be the best
Yes A seems to be the best pick here.