Question of quality planning

PMP Fighter's picture

Which of the following statements concerning quality planning is correct?

A. Quality planning should be performed regularly throughout the project.
B. Quality planning is done to compile a risk management plan.
C. Quality planning is done only during project planning.
D. Quality planning is not considered during project execution.

I would go with A.
IMO, C and D are wrong becuase Q Planning can be done at any point in time during the project (let say a new govt regulation that needs to be considered for your project so you will plan quality).

w.r.t to B i think its not mandatory to complete Q.P to complete Risk management plan.

What the correct answer?

admin's picture

Yes A seems to be the best pick here.