Question related to opportunity cost...
Submitted by PMPKID2012 on Sat, 01/28/2012 - 06:44
Need help ...
Q: An organization has four projects to choose from: Project A with a NPV $45,000, Project B with a NPV $60,000, Project C with a NPV $75,000, Project D with a NPV $30,000. What is the oppurtunity cost of selecting Project C?
A. $60,000
B. $135,000
C. $30,000
D. $45,000
Please help in finding the right answer, and also how should we solve if more than 2 projects scenario is given and asks us to find out the oppurtunity cost.
Forums:


dalrsmith
Sat, 01/28/2012 - 18:49
Permalink
It will be "A", which is
It will be "A", which is $60,000. Opportunity costs is the value foregone because of taking a particular project. Because of this, you are giving up your next best option, which is $60,000. Hope this helps.
PMPKID2012
Sat, 01/28/2012 - 20:42
Permalink
Thanks
Thanks, it helps.