question on stakeholder analysis
Submitted by amber on Fri, 09/21/2012 - 12:09
On a stakeholder analysis grid of Influence and impact, the scale is one to five with five being the highest on each coordinate. The project sponsor would have what rating on the grid?
| A. | Infl = 2.1 and Imp = 4.8 |
| B. | Infl = 5 and Imp = 1 |
| C. | Infl = 4.7 and Imp = 6.3 |
| D. | Infl = 4.6 and Imp = 4.3 |
Correct answer is D, can anyone tell me how it has been calculated.
The project sponsor is a stakeholder that would have high ratings on both axes of an Influence-Impact grid. 'A' and 'B' do not fit this criteria and 'C' is off-scale.
Forums:


sspawar
Fri, 09/21/2012 - 16:08
Permalink
This question is perhaps
This question is perhaps from insite. velociteach.com/andy crowe
Sponsor have high influence and high impact in any project
first of all are you agree this point or not tell me?
if yes
then very easy to explain
mkar
Fri, 09/21/2012 - 18:03
Permalink
my analsysis
My piece of analysis is:
The scale is 1 to 5, so option "C" is not the correct answer as it has Impact 6.3
A & B are not correct as it has influence of 2.1 and impact rating of 1, which is low when compared to opetion "D". In reality sponsor has high impact and influence on the project.
So, the quick answer is "D".
mkar