Risk Mangement Ques?
Submitted by kmrk on Mon, 12/19/2011 - 00:54
A system development project is nearing closing when a previously unidentified risk is discovered. This could potiantially affects the project's overall ablity to deliver. what should be done next?
A. Alter the project sponsor of potential impacts to cost, scope or schedule.
B. Qualify the risk
C. Mitigate this risk by developeing a risk response plan
D. develop a workaround.
Post your answers to discuss further.
Forums:


admin
Mon, 12/19/2011 - 13:45
Permalink
Before you do something, you
Before you do something, you must Qualify the risk.
kmrk
Mon, 12/19/2011 - 20:33
Permalink
Thanks Admin, thats the
Thanks Admin, thats the answer, I choose D work around which was wrong.