Scope Question
Can someone please confirm the answer to this question? I don't think the answer that i have is right.
Thanks
Project Scope is
A) The features and functions that are to be included in a product or service.
B) The work that must NOT be done in order to deliver a product with the specified features and functions.
C) part of the project charter
D) part of SOW


My answer is B.What is the
My answer is B.
What is the answer you have?
My answer B as well
More clarification check on project scope statement.
Project scope statement may include:
Product scope
project scope
product acceptance criteria
deliverables
What is not require in the project
constraints and any assumptions
My Answer is 'A' Product
My Answer is 'A'
Product scope is all about defining what a product can do in terms of features and functionality.
D) part of SOW
• Product scope. The features and functions that characterize a product, service, or result; and/or
• Project scope. The work that needs to be accomplished to deliver a product, service, or result with
the specifi ed features and functions.
D makes the most sense
The correct answer is D.
B is definately wrong because project scope is the work that must be done in order to deliver a product with the specified features and functions.
lets eliminate
Lets look at all the options one by one.
A: Features and functions that are to be included in a product of service -- Product Scope so not the right option.
B: the work that must not be done in order to deliver a product with the specified features and functions, this cannot be the option as this is talking about the product scope again, and the scope would anyways talk about what should be done and does not document the opposite.
C: Part of the project charter -- Yes the project charter does include the scope of the project
D: SOW : SOW should be a part of the project charter, as SOWs are an input to the project charter. C includes D.
I would go with C.