Sequence of close project

 Can someone please confirm the below path?

 

Get formal acceptance

write lessons learned

release the team

close the contract

close project

 

QUESTION: Where will the conduct procurement audit fits into this. Is it after 'close the contract', then how will it make through the lessons learnt?

 

 

Let me share my idea, refer to RITA.

1.close the (procurement) contract

2.Get formal acceptance

3.write lessons learned

4.release the team

5.close project

 