Small Project Question
Submitted by raza82 on Mon, 02/04/2013 - 12:24
You are managing a small project with five team members working part-time.
At the beginning of every week, you orally allocate work to all the team members.
This is an example of:
Choice 1 Work Authorization System
Choice 2 Improper Planning because team members do not know in advance what needs to be done at what time
Choice 3 Project time management plan
Choice 4 Project flexible time management plan
Forums:


prakharsidana
Mon, 02/04/2013 - 13:06
Permalink
answer
My choice in A.
sunitaPMP
Mon, 02/04/2013 - 21:04
Permalink
option 1?
option 1?
daso
Mon, 02/04/2013 - 21:11
Permalink
choice 2
choice 2. never assign tasks orally without having a plan... (professional responsibility)
sspawar
Tue, 02/05/2013 - 00:26
Permalink
no pmbok days - plan may be
no pmbok days - plan may be formal or informal. read pmbok -- putting any key word in pdf search box.
op 1 is right.
Connect2pmzilla
Tue, 02/05/2013 - 00:46
Permalink
Option 1 is right
Option 1 is right
raza82
Tue, 02/05/2013 - 04:44
Permalink
According to the simulator...
Choice 1:
A work authorization system is a collection of formal
documented procedures that specifies how project work
is authorized to ensure that work is done by the identified
organization at the right time and in the proper sequence