The stakeholders’ have most influence on a project during?
Submitted by PMP Fighter on Thu, 03/20/2014 - 09:41
The question:
The stakeholders’ have most influence on a project during : A. During the planning phase.
B. In the beginning of the project.
C. Throughout the project.
D. During the execution phase.
I choose C, but the answer is B.
The mock exam provider explanation :
Stakeholders' influences are at the peak in the beginning of the project.
Refer Page 39, 40 of PMBOK® Guide - Fifth Edition.
Is it wrong?
Forums:


interservicio
Thu, 03/20/2014 - 12:42
Permalink
B is the correct answer
B is the correct answer.
Stakeholders have more influence in the beginning when they give most of the requierements.
Are stakeholders influential throught all the project? YES ¡¡.
When are they MORE influential? In the beginning.
saketbansal
Thu, 03/20/2014 - 16:17
Permalink
PMBOK Guide Page No 40 "The