subsequent costs?
Submitted by PMP Fighter on Thu, 04/03/2014 - 02:34
Following project data are given to you
a) Target price = $90000
b) Ceiling price = $100000
c) Customer's share of cost overruns = 70%
d) Target cost = $80000
You are requested to and out point at which the seller will assume all subsequent costs:
A $ 104286
B $ 80000
C $ 14286
D $ 94280
Forums:


aliahmed
Thu, 04/03/2014 - 10:12
Permalink
I think D is answer
used this formula PTA= ( CP - TP ) / Y% + TC
Thaen i get this number 94285 and is near to (D) but im not sure .