Activity duration question
Submitted by sajays on Sun, 04/07/2013 - 03:43
Need answer to the question and logic pls. I have a feeling that the exam site has wrong answer to this question. Please explain the answer
Activity A has a FF relationship with Activity B. Activity A has a duration of 7 days. Activity B has duration of 5 Days and 3 days lag. What is the total duration of Activity A and B?