Reserve analysis - Need clarification
Submitted by ilasubbu on Sun, 11/25/2012 - 20:20
Hi All,
I have query on contingency reserve & management reserve. PMBOK & Rita says, contingency reserve is considered to define cost baseline and management reserve is considered for determining the budget. In other ways, for a budget both the reserves are to be considered but for cost baseline only contingency reserve is considered.
With this understanding, I have attempted to answer a question which was wrong. The question is,