Can someone just explain to me the below questions.
An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day g, and a late finish (LF) of day ig. The activity:
- is on the critical path.
- has a lag.
- is progressing well.
- is not on the critical path.
Answer D