Budget Estimate as per PMBOK
Submitted by manishpmp on Mon, 07/09/2012 - 14:35
Can someone pleas help me with the Budget Estimate as per PMBOK. Are the following correct.
ROM = +/- 50%
Budget Estmate = -10% to 25%
Definitive Estimate = -5% to 10%
Kindly let me know if these are correct to use in PMP exam.