PMP Exam Tip: What’s an Example of a Start-to-Finish Relationship?

The Precedence Diagramming Method (PDM) is a tool for scheduling and sequencing events in a project plan based on their relationships with other events. The model allows you to visually map activities and their dependencies. Within this model there are four types of dependencies or logical relationships that are possible: finish-to-start (FS), finish-to-finish (FF), start-to-start (SS), and start-to-finish (SF).