PMP Exam Tip: What Is The Difference Between Mandatory And Discretionary Dependencies?
Submitted by pmpodcast on Thu, 06/28/2012 - 14:19
In the project management world, dependencies determine the order in which various activities should be completed. These dependencies usually documented as an activity attribute and help in sequencing the activities on the project schedule network diagram. As you prepare for your PMP exam, it is important to know the difference between discretionary dependencies and mandatory dependencies.