Another Probability Simplified Solving Technique
Submitted by projmanpro on Mon, 04/23/2012 - 11:13
One asks me to offer a simplified probability calculation technique to this question:
Activity 1 has an optimistic estimate of 7 days, a most likely estimate of 16 days and a pessimistic estimate of 25 days. What is the approximate calculated probability that the activity will be finished in 10 to 22 days?
A. 95.4%
B. 50.0%
C. 99.7%
D. 68.3%