Risk Qn 2

 Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest will

prevent your equipment from arriving on time. You identified a risk response strategy for
this risk and have arranged for a local company to lease you the needed equipment until
yours arrives. This is an example of which risk response strategy?
A. Transfer
B. Acceptance
C. Mitigate
D. Avoid