Question #4

 

After performing risk analysis, you fin that close to 50% of the risks are technology risks.  What will you do next?

 

A. Develop a risk response strategy for all the risks that require a response according to plan

B.Develop a risk response strategy for all the technologoy risks that require a reponse accoring to plan

C. Acquire subject matter experts and highly qualified resources

D. Develop a risk response strategy for all the techology risks

 