A Risk Question
Submitted by Jgrind07 on Sun, 04/28/2013 - 03:10
Forums:
I have been doing a mock test in a mobile PMP application and came across this question.
A risk is not realized during the intended timeframe. What should the project manager do next?
A. Upadte the risk responce plan
B. Update the WBS
C. Update the project schedule
D. Identify secondart risk.
What is your choice and explain your rational behind your choice?
Thanks