Contingency reserve. Who is right. Rita or Scordo?
Submitted by y0zh on Tue, 04/23/2013 - 12:13
Forums:
Jackie is the project manager of large project. During the Determine Budget phase, she identifies that contingency reserves need to be made for unplanned but potentially required changes that could result from realized risks identified in the risk register. Which of the following is true about reserves?