During project executing a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. What would be the LEAST effective thing for the project manager to do?
A review the quality plan
B continue the perform quality assurance process
C revire the process scope statement
D hold a meeting on the issue