1) The procurement management plan is an input to identify stakeholders because:
A) The procurement statement of work includes a complete list of project stakeholders
B) All parties to the contract are stakeholders
C) All stakeholders must receive a copy os the contract
D) The plan includes the result of market research to identify additional stakeholders