Duration Estimates Questions
Need help, with the following questions:
Question: All the following statements regarding the creation of duration estimates are correct EXCEPT:
(1) Mathematical analyses like CPM, GERT and PERT indicate the dates on which the activity can be scheduled, given resource limits and other constraints
(2) Duration compression techniques, including fast tracking and crashing, can help in decreasing the project schedule
(3) WBS classification allows for useful activity ordering and sorting