WBS Activity
You've constructed the WBS for your recent project. You've requested that the subproject managers report to you in three weeks with each of tehir individual WBS contructed. Which statement is not true regarding the subproject managers' WBS?
A) The work package level is decomposed to create the activity list.
B) The work package level is the lowest level in the WBS
C) The work package level faciliaties resource assigments.
D) The work package level facilities cost and time estimates.
