technical work completed - confusing

 Hi,

All technical work is completed on the project. Which of the following remains to be done?

a. verify scope

b. plan risk responses

c. create a staffing management plan

d. complete lesson learned

answer given is d. In my opinion it is confusing. I answered a.: is it not that after the technical work is completed it needs to be verified?