technical work completed - confusing
Submitted by al.zo on Wed, 04/10/2013 - 20:16
Forums:
Hi,
All technical work is completed on the project. Which of the following remains to be done?
a. verify scope
b. plan risk responses
c. create a staffing management plan
d. complete lesson learned
answer given is d. In my opinion it is confusing. I answered a.: is it not that after the technical work is completed it needs to be verified?